Last Day Worked DFR / recap story
Big Win
Harper’s Landing moved much closer to finish after beating the rain.
Top stakes, berm matting, pond wrap-up, and Monday as-built follow-up were called out.
Production Highlight
Westside Logistics access road stone placed.
Next focus is pond/spring issue, long reach setup, muck pullback, and drainage to sumps.
Weather / Risk
Rain drove several adjustments.
Crews were sealing up ahead of weather; some work should be checked against DFR actuals on Monday.
Open schedule window
May 4–15
Supers tracked
6
Source confidence
Seed
Idle signal
Manual
Today’s Plan from 2-week + daily call
Russell
Sisters of Mercy
Ryan Pruitt starts change-order work: rake/remove 3–4 inches of debris from solar farm clearing area; target mid-week completion.
Russell
Harper’s Landing Pond
David Skiba returns to as-build pond; Jeff helps and fixes punch items that need to be addressed.
Joe
Jenkins Dairy / Gastonia Industrial
Shawn Chapple / Sean Moore continue pad cut, route suitable fill east, oversized rock to crushing, and seal up ahead of weather.
Joe
Westside Logistics
Matt / Lee address pond spring, prep pumps, receive long reach, pull muck back, and keep pond draining to sumps.
Eugene
Jenkins Road / Westlake
Wesley/Shannon pipe/invert work; Travis fire risers; Spectrum coordination for offsite storm drain conflict.
Keith
Belmont Abbey / Westside / YMCA
ABC/ditch grading, paving windows, truck-court stone, speed bump repair, and Surface 9.5C paving per Gantt windows.
Jon
Jenkins Dairy
Joshua Neely: grade Sta. 20+00–24+50, curb Sta. 11+00–20+00, proof roll/backfill, potential paving.
Idle / Sell Work capacity watch
?
Idle crews need confirmation
First version flags missing assignments instead of guessing. Pull from Monday call + DFR closeouts next.
Possible opening: Russell crew
Harper’s Landing is moving to as-built/punch; Jeff/Ryan shift to Jenkins Dairy week of May 11.
Possible fill work
Small grading, cleanup, punch, stone, erosion control, and quick paving prep are the work types to sell/fill.
Equipment check needed
Most unit IDs were not confirmed in schedule posts. Equipment availability should come from VisionLink/equipment dashboard.
Changed Since Schedule watch list
Weather / rain exposure
Seal-up, pond pumping, and wet-area access are the biggest immediate variables.
Jason not on 05/01 call
Do not infer Jason plan from Rover’s earlier mistaken recap formatting.