Monday, May 4
Seed view • 05/01 recap + Rover/Jamie schedule
Yesterday's story
Rain recovery + closeout push
Harper’s Landing advanced; Westside got access-road stone down.
Today’s focus
Finish, pump, grade, pave
Closeout/punch work plus wet-area recovery and Jenkins Dairy production.
Main risk
Weather + wet access
Ponds, pumping, and seal-up decisions drive the day.
Capacity watch
Confirm idle
Find crews/equipment we can sell into quick-turn work.

Last Day Worked actual story

Harper’s Landing moved closer to finish.

Russell called out finally beating the rain. Top stakes, strong matting, pond wrap-up, and Monday as-built follow-up are the closeout thread.

Westside got stone down on the pond access road.

Next operational story is keeping the pond draining, receiving long reach, pulling muck back, and protecting access.

Rain changed the plan.

Several crews were sealing up, shifting to weather-safe work, or waiting on conditions/materials. Monday DFRs should confirm misses and carryover.

Today’s Plan daily call + 2-week

RussellCloseout

Harper’s Landing Pond

David as-builds pond; Jeff handles punch/fix items. Watch for anything blocking final closeout.

RussellGrading

Sisters of Mercy

Ryan starts change-order debris removal/raking from solar clearing area; target mid-week completion.

JoeMass grading

Jenkins Dairy / Gastonia Industrial

Shawn / Sean continue pad cut, route suitable fill east, oversized rock to crushing, and seal up ahead of weather.

JoeWet area

Westside Logistics

Matt / Lee address pond spring, set pumping plan, receive long reach, and keep drainage to sumps.

EugeneUtilities

Jenkins Road / Westlake

Wesley/Shannon pipe and invert work; Travis fire risers; Spectrum coordination on storm conflict.

Keith / JonPave + site

Belmont / Westside / Jenkins Dairy

ABC/ditch grading, paving windows, truck-court stone, speed bumps, curb/proof roll/backfill.

Idle / Sell Work action board

?

Idle crews not confirmed yet

Do not guess. Confirm from Monday call, DFR closeouts, and equipment availability.

Ask: who is open by lunch / tomorrow?

Likely opening: closeout/punch crews

Harper’s Landing appears to be moving from production into as-built/punch. Watch Jeff/Ryan availability before Jenkins Dairy week of May 11.

Sell: cleanup, stone, erosion, punch

Equipment availability is next

Schedule posts rarely confirmed unit IDs. Tie this panel to VisionLink/equipment dashboard before calling anything truly available.

Need: operators + machine IDs