Last Day Worked actual story
Harper’s Landing moved closer to finish.
Russell called out finally beating the rain. Top stakes, strong matting, pond wrap-up, and Monday as-built follow-up are the closeout thread.
Westside got stone down on the pond access road.
Next operational story is keeping the pond draining, receiving long reach, pulling muck back, and protecting access.
Rain changed the plan.
Several crews were sealing up, shifting to weather-safe work, or waiting on conditions/materials. Monday DFRs should confirm misses and carryover.
Today’s Plan daily call + 2-week
Harper’s Landing Pond
David as-builds pond; Jeff handles punch/fix items. Watch for anything blocking final closeout.
Sisters of Mercy
Ryan starts change-order debris removal/raking from solar clearing area; target mid-week completion.
Jenkins Dairy / Gastonia Industrial
Shawn / Sean continue pad cut, route suitable fill east, oversized rock to crushing, and seal up ahead of weather.
Westside Logistics
Matt / Lee address pond spring, set pumping plan, receive long reach, and keep drainage to sumps.
Jenkins Road / Westlake
Wesley/Shannon pipe and invert work; Travis fire risers; Spectrum coordination on storm conflict.
Belmont / Westside / Jenkins Dairy
ABC/ditch grading, paving windows, truck-court stone, speed bumps, curb/proof roll/backfill.
Idle / Sell Work action board
Idle crews not confirmed yet
Do not guess. Confirm from Monday call, DFR closeouts, and equipment availability.
Ask: who is open by lunch / tomorrow?Likely opening: closeout/punch crews
Harper’s Landing appears to be moving from production into as-built/punch. Watch Jeff/Ryan availability before Jenkins Dairy week of May 11.
Sell: cleanup, stone, erosion, punchEquipment availability is next
Schedule posts rarely confirmed unit IDs. Tie this panel to VisionLink/equipment dashboard before calling anything truly available.
Need: operators + machine IDs